Labour budget and money

Check a job is running to the days you quoted, log what you spend, and see the profit as you go.

Optional

Jobs is optional. If you don't see Jobs in your menu and want it, ask us to switch it on.

Who can use this: owners and estimators. Crew never see these figures.

Set the labour budget

The Labour budget card on a job's Overview tab compares the days worked with the days you allowed. Set it when you start the job.

  1. Open the job's Overview tab.
  2. In Days allowed, type the days you allowed for the job. Count each person's day: two people for four days is 8.
  3. Tap away from the box. It saves.

If the quote's labour lines are in days or weeks, you'll see a button such as Use the quote's 8 days. Tap it to use that number. Check it first: "8 days" for a team of two may mean 16 person-days.

To remove the budget, clear the box.

What the card shows

Line What it means
Days worked Person-days worked so far, and how many are left
Job pack Tasks done, out of all tasks
Labour cost What labour has cost so far, against the labour cost on the quote
Planned finish The last day a team is booked, or No team booked
Planned days Person-days on the crew plan (only with the Crew area)

The status

Status What it means
On track The days used are keeping pace with the job pack
Watch The days used are running well ahead of the job pack (for example 60% of the days gone, 40% of the tasks done), or the job is past its planned finish
Over budget More days worked than allowed, or labour has cost more than the quote

A line above the bar says it in words, for example Behind — 6 of 10 days used, job pack 40% done. Jobs on Watch or Over budget also show on the Dashboard.

Tip

The job pack is the only measure of progress. If it isn't ticked off, a job can look behind when it isn't.

How labour is counted

It depends on whether your business has the Crew area.

  • With the Crew area: labour comes from the days your crew are marked in, at each person's day rate. There's nothing to log on the job.
  • Without it: you log labour days on the Labour & costs tab (below). The days count once for each person in the team, using the team's Headcount.

Log labour days

This is for businesses without the Crew area.

  1. Open the job's Labour & costs tab.
  2. Under Log labour days, pick the team.
  3. Enter the Days (half days are fine) and the Date.
  4. Check the Cost (£). It fills in from the team's day rate times the days. Type over it if it's different.
  5. Tap Add labour entry.

If the team has no day rate, type the cost in, or set the rate on the Teams tab.

Log other spend

Log anything else the job costs you, such as plant hire or a skip. Materials go on the Materials tab instead.

  1. Open the job's Labour & costs tab.
  2. Under Other spend, pick the kind: Plant hire, Skip / waste or Other.
  3. Set the date.
  4. Say what it was, for example 8-yard skip.
  5. Enter the amount in £.
  6. Tap Add.

Each entry shows in the list with its kind, date and amount. The list ends with a Total (excl. materials). To delete an entry, tap the bin next to it.

More detail: old labour entries with the Crew area

If you logged labour by hand before the Crew area was switched on, those entries are crossed out and marked not counted. The crew's marked days are used instead, so a day is never counted twice. Delete the old entries if they repeat marked days.

Profit: quoted against actual

The Profit — quoted vs actual card on Overview shows whether the job is making the money you expected. Everything is ex VAT. It says Your view only: customers and crew never see it.

Row Quoted Actual so far
Revenue (net of discount) The quote, less any discount, plus accepted extra work The same
Costs Your costs for the quote lines, from the rate card when the quote was made Materials actually paid, plus labour and other spend
Profit Revenue less costs, with the margin Revenue less costs so far, with the margin

A dash means there's nothing to show yet. If a quote line had no cost on file, the card says how many.

If the actual margin falls below the minimum margin you set in Settings, the card warns you: Actual margin is below your …% floor.