Skip to content

Materials and ordering

Keep track of what a job needs, when to order it, and what you paid.

Optional

Jobs is optional. If you don't see Jobs in your menu and want it, ask us to switch it on.

Who can use this: owners and estimators, on the job's Materials tab. With the Crew area, crew can also mark materials ordered or delivered from their app: see For crew members.

QuoteSite doesn't send orders to suppliers. It keeps track of them, and reminds you in time.

Fill the materials list

If you started the job with Start and set up from quote, the list is already filled in. Otherwise:

  • Tap Add materials from the quote to add every quote line with a cost, or
  • Type a name in Add a material… and tap Add.

What each material shows

On a phone each material is a card. On a wide screen it's a row.

Field What it is
Name Tap to change it. It saves when you tap away.
Qty How much. Type anything, like 12 m² or 3 bags.
Est. cost What it cost on the quote. You can't change it.
Actual paid (£) What you actually paid. This feeds the profit figures.
Status To order, Ordered or Delivered
Order by When to order it (see below)
days ahead How many working days before the job it should be ordered

The bottom row shows the Totals for the estimate and what you've paid. To delete a material, tap its bin.

When to order

Each material's order-by date is the job's first booked day, less its lead time in working days (Monday to Friday). The line above the list tells you the first booked day.

  • Your usual lead time is set in Settings, on the Jobs tab. It's 5 working days unless you change it.
  • To change it for one material, type a number in its days ahead box.

The tag tells you where each material stands:

Tag What it means
Overdue · was a date It should have been ordered already
Due soon · by a date Order it today or within 2 working days
Order by a date There's still time
Set when a team is booked No team is booked yet, so there's no date
Ordered or Delivered Done

The Dashboard warns you about anything overdue or due soon.

Mark something ordered or delivered

  1. Find the material.
  2. Change its Status to Ordered or Delivered.
  3. When you know the price, enter it in Actual paid (£).

Under the status you'll see who marked it and when, for example Ordered by Dave, Tue 3 Nov.